Project number
VSS2014/411
Project title
Enabling Realistic Benchmarking of the Renewal Maintenance of Cantonal Roads (BORMAC)

Texts for this project

 GermanFrenchItalianEnglish
Key words
-
-
-
Anzeigen
Short description
-
-
-
Anzeigen
Project aims
-
-
-
Anzeigen
Berichtsnummer
Anzeigen
-
-
-

Inserted texts


CategoryText
Key words
(English)
Benchmarking; Road Networks; Renewal Management; Infrastructure; Cost Function;
Short description
(English)

A pilot study (2013) concluded that a total performance benchmark for road renewal could be implemented for all cantons if certain data and estimation issues were resolved. Partial performance benchmarks of high quality can be implemented even today. We propose to carry out the follow-up steps.

In essence, we propose to collect data at the level of road sections from all cantons, including the most recent two inspections; to transform it into a common data structure; and then to calculate the benchmarks. A concise ‘fact-sheet’ presentation will demonstrate how the results can be used in practice. However, before the proposed total performance benchmark can be calculated, research is required to estimate realistic compensation for various ‘environmental’ conditions like steepness or urbanity. This requires the collection of a second set of data; a cooperation with a second existing project at the IBI will reduce overall data collection effort.

The proposed estimation of the cost function from engineering relationships is distinct from traditional approaches that use generic functions, which are not specific to roads. A cross-disciplinary approach including researches from EMPA will create a synthesis of existing engineering and economic models. We believe that modern computing techniques makes this approach viable today.

Project aims
(English)
Superficially, cantons appear to vary up to 10:1 in the cost efficiency of road renewal expenditure. If it is a data problem, then it masks potential waste. If it is waste, then clear measures are needed to identify the cause. As is, benchmarking of cost efficiency is strongly inhibited.
This project's goals are four fold. 1) Define standards for comparable data on expenditure. 2) Implement a prototype comparable benchmarking concept on cost efficiency. 3) Estimate the cost implications of the exposure to environmental factors like ‘steepness’. 4) Implement a set of partial performance indicators to identify specific causes of inefficiency.
Berichtsnummer
(German)
1658